Ground anchor design in sand over marl: worked example
Bond length, tendon, ground cone, proof and lock-off loads of a 4-strand tieback bonded in sand and marl, to EN 1997-1 A1:2013, by hand and with the free tool.
Open this example in the tool The link loads all inputs below.
Problem
A 6 m high soldier pile wall is held by one row of permanent strand anchors at 2.0 m spacing. The service load of one anchor is FServ,k = Pk = 350 kN. The anchor head is 3.0 m below the ground, inclined 25° below the horizontal, with a 7.0 m free length and an 8.0 m bond length drilled at 150 mm. Check the grout–ground bond, the tendon, the grout–tendon bond and the ground cone to EN 1997-1:2004 + A1:2013, find the bond length the ground needs, and set the proof and lock-off loads. A rock bolt check closes the example.
| Fill, 0–4.0 m | γ = 18 kN/m³ (no bond in this layer) |
| Medium dense sand, 4.0–7.5 m | γ = 19 kN/m³, qs = 200 kPa (FHWA range 100–250 kPa) |
| Marl (weak rock), below 7.5 m | γ = 22 kN/m³, qs = 400 kPa (range 300–800 kPa) |
| Water table | 6.5 m below the ground |
| Tendon | 4 strands Y1860S7 15.2 mm, At = 4 × 140 = 560 mm², fp0.1k = 1600 MPa, fpk = 1860 MPa |
| Factors | γE = γServ = 1.35, γa,ULS = 1.1, model factor γRd = 1.4, γs = 1.15 |
1. Geometry and design load
2. Grout–ground bond
With qs the resistance of a layer is π D qs L. The calculated value stands in for the measured resistance of suitability tests and is divided by the model factor before the partial factor.
3. Tendon, grout and ground cone
The ground cone and the grout are far from governing. The bond (1.60) and the tendon (1.65) are close, which is the usual aim: the tendon should not be much weaker than the ground, otherwise the proof load cannot show the ground resistance. Detailing: free length 7.0 m ≥ 5 m, bond starts 4.5 m beyond the slip surface (≥ max(1.5 m, 6/5)), 6.0 m of ground over the bond (≥ 4.5 m), spacing 2.0 m ≥ max(4 · 0.15, 1.2) m, service load 350 ≤ 0.65 · 1042 = 677 kN.
4. Proof and lock-off loads
Measured readings pasted in the test tab give the apparent free tendon length from the unloading. For example an unloading of 468 kN with a recovery of 43 mm gives Lapp = 109.2 · 43 / 468 = 10.0 m, inside the 7.1–12.5 m band.
5. Rock bolt
A ribbed B500B Ø25 bolt, 4.0 m long in a 45 mm hole, crosses a wedge face 1.6 m behind the face; rock–grout bond 1.0 MPa, grout–bar bond 3.0 MPa, plate 250 kN, 1 mm corrosion loss.
Hand calculation and tool
| Hand calculation | Tool | |
|---|---|---|
| Rcalc / RULS,d | 1166 / 757 kN | 1166 / 757 kN |
| FoS bond / tendon / grout / cone | 1.60 / 1.65 / 4.31 / 5.19 | 1.60 / 1.65 / 4.31 / 5.19 |
| Bond length needed | 5.7 m | 5.7 m |
| Pp / P0 | 520 / 350 kN | 520 / 350 kN |
| Elongation band at Pp | 30.4–53.5 mm | 30.4–53.5 mm |
| Rock bolt Tk | 226 kN | 226 kN |
The calculated bond resistance is a preliminary estimate. EN 1997-1 bases the anchor resistance on investigation or suitability tests, and every working anchor gets an acceptance test to the proof load.
References
- EN 1997-1:2004 + A1:2013. Eurocode 7: Geotechnical design – Part 1: General rules (Section 8 Anchors, Annex A).
- EN 1537:2013. Execution of special geotechnical works – Ground anchors.
- EN ISO 22477-5:2018. Geotechnical investigation and testing – Testing of geotechnical structures – Part 5: Testing of grouted anchors.
- Hoek, E., Kaiser, P.K. & Bawden, W.F. (1995). Support of Underground Excavations in Hard Rock. Balkema, Rotterdam.
- Littlejohn, G.S. & Bruce, D.A. (1977). Rock Anchors – State of the Art. Foundation Publications, Brentwood.
- Sabatini, P.J., Pass, D.G. & Bachus, R.C. (1999). Ground Anchors and Anchored Systems. FHWA-IF-99-015, Geotechnical Engineering Circular No. 4.
Worked example by Martin Hostnik, updated 2026-11-21. Results are for checking and preliminary design; verify them for your project. Questions or a correction: [email protected].